Facilities / Meta

Meta — Luleå campus (3 buildings)

Sweden · Operational

Status Operational
Capacity (MW) 723.8 (third-party tracker figure — UNVERIFIED; may reflect total site power not IT load) Sources: dgtlinfra.com · www.datacentermap.com
Power source claim 100% renewable (hydro-rich Luleå grid) — operator claim Sources: datacenters.atmeta.com
Published PUE UNVERIFIED at site level (Meta publishes fleet-wide PUE)
Ownership / jurisdiction Meta Platforms, USA (self-build, sole tenant) Sources: datacenters.atmeta.com
AI / GPU relevance Hyperscale own-use; AI training capacity at site UNVERIFIED
Verification notes 723.8 MW figure needs methodology check — likely grid connection capacity
Fields marked UNVERIFIED could not be confirmed against a public source. We publish uncertain data as uncertain.